Bengaluru: The opening of Jakkur railway overbridge came as a relief to thousands of commuters in north Bengaluru. But why did a 443-metre bridge take 15 years to complete, even though it is located in the constituency represented by Bengaluru development minister Krishna Byre Gowda, known for his proactive approach to development issues?The Rs 69.6-crore project, initiated by South Western Railway (SWR) in 2011, was stalled in 2014 over land acquisition hurdles before being handed over to the then Bruhat Bengaluru Mahanagara Palike (BBMP) in 2018. The civic body issued a fresh work order only in 2024, with land acquisition accounting for Rs 43.5 crore of the total expenditure. Five major factors contributed to the delay:Land Acquisition ProblemsA total of 6,733sqm of land had to be acquired from 48 properties. Most owners rejected compensation options such as transferable development rights (TDR) and demanded cash. This pushed land acquisition costs well beyond construction costs. In 2017, BBMP adopted the direct purchase scheme under the Karnataka Municipal Corporations Act and acquired 33 properties for Rs 25 crore.Project Abandoned by SWRSWR, which started the project in 2011, halted construction in 2014, citing land acquisition issues. “The railways handed the project to BBMP on an as-is-where-is basis after encountering land acquisition issues,” Bengaluru development minister Krishna Byre Gowda said.BDA’s Arkavathy Layout PropertiesTwo properties required for the project were part of Bangalore Development Authority’s Arkavathy Layout. Even as BBMP acquired other land through compulsory acquisition, deposited compensation with the court and proceeded with construction, these properties remained a hurdle. The allotments were under the oversight of the Justice Keshavanarayana Committee. A proposal to acquire the required land was placed before the committee, which cleared the land needed for the bridge’s down ramp only in Aug 2025.No Timely Re-tenderingAfter SWR exited in 2018, BBMP took nearly six years to issue a fresh work order in 2024. Pending land acquisition was cited as the reason for the delay. Gowda also blamed the previous BJP govt for failing to push the project forward. “From 2018 to 2023, there was no progress when our govt was not there,” he said.Lack of Regular Follow-upGowda said he began proactively following up on the project after DK Shivakumar became deputy chief minister and directed officials to expedite work. “After Shivakumar became DCM, he allocated funds to complete the project and provide cash compensation for land acquisition,” the minister said.