For more than five years now, Chennaiites have been putting up with shrinking roads, traffic diversions and bottlenecks, as Chennai Metro’s blue barricades take over busy roads and junctions. But, relief could be around the corner at Luz Junction, Panagal Park, Greenways Road and Lighthouse, where construction is expected to reach crucial milestones. From the closure of tunnelling shafts to completion of underground stations, barricades are expected to come down in the next two years in phases. Here is what’s happening behind the barricades:Thirumayilai: Luz Junction motorists face two more years of metro work as utility hurdle delays stationMotorists who have endured traffic restrictions at Luz junction for three years may have to wait at least another two years, with construction of Thirumayilai interchange station facing fresh hurdles. The station, where Corridors 3 and 4 intersect, is now targeted for completion by Dec 2028.Engineers constructing the station’s diaphragm wall have encountered a large metro water pipeline, leaving a section of the wall unfinished. Excavation inside the station box cannot begin until the outer walls are completed.“We must now request a traffic diversion to shift that utility and complete the D-wall construction. Once the D-wall is completed, we will excavate the Corridor 4 portion of the station box, which will begin in a month,” a metro rail official said.Meanwhile, two tunnel boring machines (TBMs) that crossed Thirumayilai from Lighthouse are approaching Alwarpet on Corridor 4. Another TBM is tunnelling from RK Salai towards Mandaveli on Corridor 3. After completing the drive, it will be deployed from Mandaveli towards RK Salai.The interchange involves four tunnels stacked underground in a tight, congested area, with two Corridor 4 tunnels sandwiched between two Corridor 3 tunnels. “We chose this arrangement to facilitate better passenger movement,” an official said.Work had also stalled earlier because shops at the site could not be vacated for nearly a year.Lighthouse: Metro takes shape at Marina, but opening may wait till March 2028Chennai’s largest underground metro station is taking shape on Marina Beach, but Lighthouse station on Corridor 4 may not be ready before March 2028.Track-laying has begun inside the tunnels, while construction of station entry and exit structures and rooms is under way, a Chennai Metro Rail Ltd (CMRL) official said. A pedestrian subway is also being built to connect the station with an entry/exit point on the other side of Kamarajar Salai, near Queen Mary’s College.“Construction is at an advanced stage. We could complete the work faster because this is an off-road station and did not require decking. Since Thirumayilai station may not be ready, we are exploring the possibility of initially operating Corridor 4 services through Thirumayilai,” the official said.The originating station of the Lighthouse–Poonamallee Bypass corridor, Lighthouse will measure 415m by 30m. It will have space to accommodate eight driverless trains, allowing them to be parked and kept ready for daily operations.The station will also have flood gates at its entry points, designed to close automatically when floodwater reaches a specified level.Greenways Road: Station may be ready by Aug 2027, but passengers could still be left waitingGreenways Road Metro may be ready by Aug 2027, but that does not mean passengers will be able to use it anytime soon. The station’s civil work is expected to be completed by then, but its opening will depend on the progress of work at other stations along the corridor, particularly Thirumayilai, Indira Nagar and Taramani.Located inside a playground, the underground station on Corridor 3 (Madhavaram–Sipcot) is nearing completion on the outside, with interior work and rooms still being developed. However, trains cannot operate through this stretch without the adjoining stations being ready.“Greenways Road will be completed, but the problem is the stations along the corridor, such as Thirumayilai, which has stacked tunnels. Indira Nagar and Taramani station locations are entirely in rock strata. We will not be able to operate Greenways Road without the surrounding stations,” a CMRL official said.Construction has faced delays linked to underground utilities in nearby stations and difficult tunnelling conditions. At Mandaveli, four major water and sewer pipelines had to be diverted before diaphragm wall construction could proceed. The Greenways Road–Mandaveli tunnel drive, initially expected to take six months, took nearly two years.Panagal Park: Panagal Park barricades to come down early 2027Motorists crossing T Nagar could get some relief early next year, with CMRL planning to remove the barricades around Panagal Park by Jan 2027 once tunnelling work is completed. The station being built beneath the park is expected to be ready by mid-2027.A TBM, launched from Panagal Park towards Boat Club, is close to its destination. Tunnelling is expected to be completed by Dec-end, after which CMRL plans to close the launching shaft near the park and remove the barricades. Only those around the park itself will remain, an official said.“The TBM which we launched in Panagal Park is now nearing Boat Club. Tunnelling will be completed by Dec-end, after which we will close the shaft near Panagal Park and remove all the barricades by Jan 2027. Only the barricades around the park will remain,” the official said.The 310m-long, 20m-wide underground station will have crossover tracks, allowing trains to switch tracks during emergencies and access the depot. Track-laying is under way on the underground stretch towards Vadapalani, while rooms are being built inside the station.Once the 3.5km Vadapalani–Panagal Park stretch opens, commuters from Poonamallee and Porur can travel directly to T Nagar by metro.