MUMBAI: Central Railway’s century-old Matunga Workshop is now equipped with 2 MW of rooftop solar capacity, which is projected to meet 42.5% of its electricity requirement and save the national transporter around Rs 1.90 crore annually.The two grid-connected solar plants are expected to generate 28.56 lakh units of electricity annually. Installed under the Renewable Energy Service Company (RESCO) model, the project involves no upfront capital investment by the Railways. Private developers have funded the installations and are responsible for their operation and maintenance, while Central Railway purchases the electricity generated at pre-agreed rates.The first 1,000 kW plant, developed by SG Renewables, New Delhi, was commissioned in February 2020, while the second 1,000 kW plant, developed by Comspec Renewable, Hyderabad, became operational in March 2026. Together, the plants have a DC capacity of 2,300 kWp and comprise 5,448 solar modules and 35 inverters. Both installations have net metering facilities.Apart from reducing electricity expenditure, the solar installations are expected to prevent around 2,340 metric tonnes of carbon dioxide emissions annually, contributing to Indian Railways’ sustainability goals. The plants are equipped with remote monitoring systems to track power generation and operational performance.Established in 1915 during the era of the erstwhile Great Indian Peninsula Railway, Matunga Workshop is among the oldest railway workshops in the country. The project demonstrates how existing railway infrastructure can be utilised to generate renewable energy while reducing dependence on conventional power sources.Central Railway has also exceeded the rooftop solar installation target set by the Prime Minister’s Office. Against a target of 10.33 MWp, the zone has already commissioned 14.79 MWp of rooftop solar capacity, taking its total commissioned capacity to 22.68 MWp.