Ludhiana: Ludhiana’s ambitious canal-based water supply project has crossed the halfway mark, with 54.4% of the overall work completed and construction under way on 59 of the 70 new overhead water tanks planned across the city.The World Bank and Asian Infrastructure Investment Bank (AIIB)-funded project aims to provide treated surface water to households across Ludhiana.A major component, the water treatment plant (WTP) at Bilga village near Sahnewal, has recorded 38.64% progress, while around 32% of the work to rehabilitate existing overhead tanks has been completed.Mayor Inderjit Kaur inspected the WTP site Thursday and reviewed the progress of various components, safety arrangements and implementation of the project. Officials said the work was progressing as per schedule.The Bilga plant is crucial to the project as canal water will be treated there before being supplied to households across the city through the new distribution infrastructure.The mayor directed the executing agency and project implementation unit officials to expedite work on the overhead reservoirs while ensuring that safety and quality standards were maintained.With pipeline laying work requiring roads to be dug up across the city, Kaur also directed officials to restore excavated stretches at the earliest and minimise inconvenience to residents.Officials said several roads had already been restored after the laying of water supply lines, including stretches in Model Town, Dugri, Sarabha Nagar, Pakhowal Road, Rishi Nagar, Kitchlu Nagar, Rajguru Nagar and Barewal.Calling the project a major investment in Ludhiana’s long-term water infrastructure, the mayor asked the agencies involved to improve coordination and make efforts to complete the work within, or ahead of, the scheduled timeline.