Ahmedabad: Adani Energy Solutions Ltd (AESL) has secured a transmission project in Bihar to evacuate 2,400 MW of power from an upcoming thermal power plant. The project is expected to generate an annual tariff revenue of around Rs 500 crore after commissioning.AESL won the project through a tariff-based competitive bidding process. The transmission system will serve Adani Power’s 2,400 MW Pirpainti Ultra Super Critical Thermal Power Plant and is scheduled to be completed by the fourth quarter of 2028.The network will comprise three 400 kV double-circuit transmission lines linking Pirpainti with Jhanjharpur and Begusarai, and Begusarai with Bakhtiyarpur. It will also include two 220 kV double-circuit lines and upgrades to existing infrastructure.The project will add 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity to AESL’s portfolio.“The Pirpainti transmission scheme will create a robust evacuation system for 2,400 MW of generation capacity while strengthening Bihar’s transmission backbone,” said Kandarp Patel, CEO of Adani Energy Solutions.The project will be executed through a special purpose vehicle, Vikramshila Power Transmission Ltd. It includes the construction of four gas-insulated substations at Jhanjharpur, Bethauli and Begusarai, along with associated transmission and transformation infrastructure.